Azimut Grande 32M: chilled-water AC failure, root cause wantedAzimut Grande 32M: AC root cause wanted

Root cause: what has been done and what is still open

What this page tells you: which steps are finished, which are still open, and what would close the investigation.

Facts as recorded by the owner. Root cause not determined. No cause is asserted on this page.

Since early 2024, parts have been cleaned, bypassed and replaced, quotes issued and a replacement plant ordered. Several technical teams have attended the yacht; none has identified the root cause. This page shows which steps are complete and which are still open.

The first faults were recorded in early 2024 (controller alarms logged in January, contamination found in the chilled-water loop in February), about 6–7 months after delivery on 26 Jun 2023 and within the 12-month warranty period.

Azimut’s stated position (after-sales email, 28 Jul 2026) is that the 2024 loop contamination is technically unrelated to the 2026 failures.

No one has yet established a root cause that either links or separates the 2024 faults and the 2026 failures.

Status of each step, as of 12 Oct 2026
StepStatus
Replacement options quoted by the regional dealerDone 6 Aug 2026, revised 13 Aug
Installation labour quoted by the local contractorDone 13 Aug 2026
Replacement plant ordered (to protect the lead time)Done 7 Sep 2026
Builder on-board inspection (see timeline)Planned 27–28 Oct 2026, with the builder’s electrical subcontractor and a builder-appointed specialist
Insurer’s surveyDone 26–27 Aug 2026; the insurer advised the survey did not determine the AC cause
Joint root-cause finding (builder and manufacturer), agreed on the 30 Jul 2026 callOpen
Witnessed teardown of a failed compressor and oil analysisOpen The regional dealer advised (Sep 2026) it would not lead a root-cause investigation and recommended involving the compressor manufacturer
Cooling restored on boardOpen Waiting for the replacement plant

Why this matters

What would close it

  1. A written investigation scope agreed by the parties: who opens what, who takes samples, who keeps custody.
  2. Witnessed teardown and oil analysis of at least one failed compressor.
  3. Electrical testing of the retained drives and reactors.
  4. A dated written finding: what failed first, what contributed, and how to prevent a repeat.