Evidence held
What this page tells you: which parts, samples, readings and documents we hold for an investigator.
What has been kept and recorded, so an investigator can see what is available before offering help. Items are available on request through the help form.
| Type | What exists |
|---|---|
| Failed parts (kept under custody) | Failed compressors, unit 3 inverter drive and power module (photos), line reactors with charred terminals (photos) |
| Fluid samples | Sealed chilled-loop water and glycol sample (Jun 2026); strainer debris (photos) |
| Measurements | Insulation and winding tests (May and Aug 2026); line reactor resistance; leakage current; hull potential; transformer thermal survey and voltages |
| Controller records | Photos of Danfoss MCX alarm screens and event logs, Jan 2024 to Aug 2026 (the full fault-code table) |
| Photos | About 30 dated photos (see the photo gallery) |
| Documents | Commissioning form, service reports, the independent inspection report, correspondence log; manufacturer electrical diagram, CWS 3603 RC 400/3/50 Inverter, order 7704, 8 sheets, dated 15 Feb 2022, received 12 Oct 2026 (held privately, available to investigators on request) |
Still being sought
- Manufacturer electrical diagram for the CWS MODUL 3603 RC: received 12 Oct 2026.
- Installation manual for the installed model (the manual on board is for CWS MODUL 2402).
- Yacht-side installation wiring, earthing and bonding drawing.
- Controller parameter file and firmware version.
- Manufacturer commissioning remarks list.
- Factory chilled-water fill and glycol record.
How the evidence is organised: evidence pack checklist.